Project Phasing
To minimize disruptions to learning, the following construction phasing is being proposed.
Phase 1
December 2023 – June 2024
Demolish C-Wing & start construction of Gym and South Wing

Phase 2
June 2024 – August 2024
Proceed with construction of Gym & South Wing
Start renovation of A-Wing
Site work throughout

Phase 3
September 2024 – June 2025
Finish Gym and South Wing
Renovation of A-Wing continues
Students and staff occupy ‘A’ wing & ‘B’ wing.

Phase 4
June 2025 – August 2025
Finish new South Wing & Gym
Demolish ‘B’ Wing
Begin work on North Wing
Site work throughout

Phase 5
September 2025 – June 2026
North Wing continues
Renovation of A-Wing continues
Students & staff occupy A-Wing, Gym & South Wing

Phase 6
June 2026 – August 2026
Finish North Wing
Finish renovations
Finish site work throughout