Project Phasing

To minimize disruptions to learning, the following construction phasing is being proposed.

Phase 1

December 2023 – June 2024

Demolish C-Wing & start construction of Gym and South Wing 

Phase 2

June 2024 – August 2024

Proceed with construction of Gym & South Wing

Start renovation of A-Wing 

Site work throughout 

Phase 3

September 2024 – June 2025

Finish Gym and South Wing 

Renovation of A-Wing continues 

Students and staff occupy ‘A’ wing & ‘B’ wing. 

Phase 4

June 2025 – August 2025

Finish new South Wing & Gym 

Demolish ‘B’ Wing 

Begin work on North Wing 

Site work throughout 

Phase 5

September 2025 – June 2026

North Wing continues 

Renovation of A-Wing continues 

Students & staff occupy A-Wing, Gym & South Wing 

Phase 6

June 2026 – August 2026

Finish North Wing 

Finish renovations 

Finish site work throughout