Our Progress
MODULE 1:
Eligibility Period
December 2018 – April 2020
- District completes requirements determined by MSBA
- Spencer and East Brookfield towns voted to approve moving forward with a Feasibility Study
- Goal: Develop a plan and schematic design for a new regional high school
- Status: Complete
MODULE 2:
Forming the Project Team
May 2020 – April 2021
- Generation of School Building Sub-Committee & Selection of Owner’s Project Manager Firm
- Status: Complete
MODULE 3:
Feasibility Study
May 2021 – December 2021
Educational Visioning Sessions
Evaluation of Existing Conditions
Site Development Requirements
Develop several options, including Base Repair, Add/Reno, and All New
Narrow to a Preferred Option
Present to MSBA
Status: Complete
MODULE 4:
Schematic Design
December 2021 – Present
- Adjust & finalize design: present to the community for input
- Develop cost estimate
- Present to MSBA for approval
- Status: Complete
MODULE 5:
Funding the Project
Estimated: June 2022 – November 2022
- Present final plan to the community for vote
- Status: Scheduled
Special Town Meetings
East Brookfield: Tuesday, September 13
Spencer: Wednesday, September 14.
We are here >
MODULE 6:
Design Development, Construction Documentation & Bidding
Estimated: December 2022 – November 2023
The District and its team advance the design, generate construction documentation, procure bids and award a construction contract in accordance with the agreed upon project scope, budget and schedule as documented in the Project Funding Agreement, and the requirements contained in the MSBA’s standard contracts for Owner’s Project Management and Designer Services. The MSBA continues to monitor the project to ensure it remains on track and meets the expectation of both the District and the MSBA as defined in the Project Funding Agreement
MODULE 7:
Construction Administration
Estimated: December 2023 – August 2026
The MSBA continues to monitor progress of the project to confirm that it remains on track and meets the expectation of both the District and the MSBA as defined in the Project Funding Agreement.
MODULE 8:
Project Closeout
August 2026 – October 2027
The MSBA performs final audit to determine final total grant amounts and make final payment.